National Grid engineers laid more than 80% of the onshore cable part of the £1bn Western Link project

  • More than eighty per cent of the underground cable is laid
  • Work on the A540 is expected to finish shortly
  • Work is starting to commission the Flintshire Bridge converter station

LONDON, 28-Apr-2016 — /EuropaWire/ — More than eighty per cent of the Western Link project’s underground cable has been laid from Leasowe, at the northern tip of the Wirral peninsula, down to National Grid’s substation in Connah’s Quay.

This includes the two-kilometre stretch along the A540, the longest section being laid in a main road, and it is expected that work will be completed here shortly.

Peter Roper, Senior Project Manager said: “We appreciate that our work is affecting local residents and commuters, and we’d like to say a big ‘thank you’ to everyone for their patience so far.

“The good news is that by the end of the year we expect to have laid all the cable and joined the sections together, and completed most of the reinstatement of the land where we’ve laid the cables. We may need a handful of road closures to complete the work and if we do, we’ll post these on our website www.westernhvdclink.co.uk.”

Most of the cable is laid in trenches. The cable is brought to the site on a special transporter around 26 metres long, and a powerful winch pulls the cable into the trench. The trench is then backfilled and the land reinstated according to the requirements of the landowners and to its previous condition, as a minimum.

Joining the cables together – known as ‘jointing’ – is highly specialised work and needs to be carried out in a controlled environment. Specialist teams work inside containers, where they create two joints, one for each cable, with each joint taking between seven to ten days. Once the work is complete the containers are removed and the land reinstated.

On Deeside Industrial Park, work has progressed well with construction of the Flintshire Bridge converter station. All the buildings are complete, and all the electrical equipment needed to connect the Western Link cables to the existing national grid has been installed. Work is starting shortly on the complex, lengthy task of commissioning.

The alternating current cables needed to connect the converter station to National Grid’s substation in Connah’s Quay have been pulled through pipes installed under the River Dee, and laid underground along the banks of the river up to the substation.

“We expect to complete all the work on the alternating current cables, including reinstatement of the land, over the next few months,” said Peter Roper.

Out at sea, work is continuing to lay the subsea cable to connect to North Ayrshire, where work is continuing to construct a second converter station and install approximately four kilometres of underground cable.

If people have any queries on the project they can contact the Community Relations Team by emailing westernlink@communityrelations.co.uk or calling 0800 021 7878. They can also find more information on the website www.westernhvdclink.co.uk.

The £1 billion Western Link project is a joint venture between National Grid and ScottishPower Transmission. When complete, it will bring renewable energy from Scotland to homes and businesses in England and Wales and help the UK meet its carbon reduction targets.

Contact for media information only
Regional press officer – northeast and northwest
Jeanette Unsworth
jeanette.unsworth@nationalgrid.com
+44 (0)7785 290230
+44 (0)7785 290230

Follow EuropaWire on Google News
EDITOR'S PICK:

Comments are closed.