Dogger Bank C secures Cadeler Wind Apex vessel for installation of 87 offshore turbines

New A-class vessel is expected to join Seaway Ventus in Q3 2027 on the third 1.2GW phase of the UK offshore wind development

Offshore installation vessels and large cranes at a waterfront site beneath an orange sunset

Offshore installation vessels at sunset. Photograph supplied with the announcement; vessel identities are not specified.

Dogger Bank Wind Farm has signed an agreement with Cadeler for the newbuild Wind Apex turbine installation vessel to support its third 1.2GW phase, Dogger Bank C. Expected to begin work in the third quarter of 2027, Wind Apex will operate alongside Seaway Ventus and support installation of 87 turbines. The wider 3.6GW project, owned by SSE, Equinor and Vårgrønn, is being constructed off the north-east coast of England and is designed to generate enough renewable power for approximately six million UK homes annually upon completion.

  • Cadeler's newbuild Wind Apex is expected to join the Dogger Bank C turbine installation campaign in Q3 2027 alongside Seaway Ventus.
  • The contract supports installation of 87 turbines in the 1.2GW Dogger Bank C phase and completion work across the remaining project phases.
  • Dogger Bank Wind Farm comprises three 1.2GW phases and is designed to supply renewable electricity equivalent to the annual needs of around six million UK homes upon completion.
  • SSE and Equinor each own 40% of the joint venture while Vårgrønn owns 20%; Equinor is due to operate the completed project.
  • When is Cadeler’s Wind Apex expected to begin work at Dogger Bank C?

    The newbuild installation vessel is expected to join the turbine installation campaign in the third quarter of 2027, alongside Seaway Ventus.

  • How many turbines will Dogger Bank C install with the additional vessel support?

    The vessel will support the installation of Dogger Bank C’s 87 turbines and completion activity on the remaining project phases.

  • Who owns and will operate Dogger Bank Wind Farm?

    SSE owns 40%, Equinor owns 40% and Vårgrønn owns 20%. SSE is leading development and construction, while Equinor will operate the wind farm after completion for an anticipated 35-year operational lifetime.

  • How much renewable electricity is the entire Dogger Bank Wind Farm expected to produce?

    When complete, the three-phase 3.6GW wind farm is expected to generate enough electricity to power around six million UK homes annually.

Dogger Bank Wind Farm, the 3.6GW offshore wind development jointly owned by SSE (40%), Equinor (40%) and Vårgrønn (20%), has signed a contract with Cadeler for a second turbine installation vessel to work on Dogger Bank C, its third 1.2GW phase. The additional vessel capacity will support installation activity at the project off the north-east coast of England.

Under the agreement, Cadeler’s newly built Wind Apex is expected to join the Dogger Bank C turbine installation campaign in the third quarter of 2027. It will be available to work alongside Seaway Ventus, the project’s existing installation vessel, to help complete work on the remaining phases of Dogger Bank Wind Farm.

Wind Apex is the third vessel in Cadeler’s A-class series, designed to undertake both offshore wind foundation and turbine installation. Dogger Bank C is set to be the vessel’s first deployment following its delivery from the shipyard.

Additional capacity for Dogger Bank C’s 87 turbines

The Dogger Bank project is being developed in three phases of 1.2GW each — Dogger Bank A, Dogger Bank B and Dogger Bank C — approximately 130 kilometres off England’s north-east coast. When fully completed, the 3.6GW development is expected to be capable of producing sufficient renewable electricity to power around six million UK homes every year.

Alan Borland, Turbine Director at Dogger Bank Wind Farm, said:

“Securing additional specialist vessel capacity for Dogger Bank C is another important step in the delivery of this world-leading offshore wind project.

“Wind Apex will join the campaign as an additional turbine installation vessel, working alongside the project’s existing installation vessel to safely and efficiently install Dogger Bank C’s 87 turbines and support the completion of the remaining phases of the project.

“Together with our partners and contractors, we remain focused on the safe delivery of all three phases of Dogger Bank and the homegrown renewable energy the wind farm will provide for the UK.”

Mikkel Gleerup, CEO of Cadeler, commented:

“Dogger Bank is one of the world’s most ambitious offshore wind developments, and we are proud to support its delivery. We value the long-standing relationships we have built with our customers and see these contracts as a reflection of the trust they place in Cadeler to execute large-scale offshore wind projects safely and efficiently. The campaign will also mark the first deployment of Wind Apex, and we look forward to seeing her begin operations on a project of this scale.”

Project development and operation

The three-phase Dogger Bank Wind Farm is being built through a joint venture in which SSE and Equinor each hold a 40% interest and Vårgrønn holds 20%. SSE leads development and construction for the partners, while Equinor is scheduled to take over operation of the wind farm when it is completed. The project’s anticipated operational lifetime is approximately 35 years.

Media & events

For media enquiries and interviews, or to enquire about having a Vårgrønn team member speak at your event, contact:

Rebecca Emelie Arntsen
Communications Manager
+47 48 07 07 66
communications@vargronn.com

SOURCE: Vårgrønn

EDITOR'S PICK:

Comments are closed.